Habitus Townhomes July 2019
Construction update

Despite the blustery cold of winter, construction on Habitus Townhomes continues to gain momentum.

Throughout July, we have seen considerable progress with the completion of the below ground plumbing and the structure of the individual buildings now beginning to rise from the ground.

With over half the site’s ground floor slabs poured, we are now seeing the installation of precast concrete panels and formwork for first floor slabs.

As always, the devoted team at Beulah International are continuing to work closely with Ironside and the appointed consultants to ensure all construction details and materials are procured and installed with the utmost care.

Construction on Habitus