Construction update

Multiplex is now well and truly into the facade installation on all sides of the building. The installation of the two-tone custom windows has now reached the golden windows section and will continue to crawl up the building in the coming months.

In addition to the facade, the internal fit-out works are well underway with services installed on the lower floors and plaster installation to commence in January.