Paragon July 2019
Construction update

We are pleased to share that momentum on Paragon has continued to build in July with the below-ground-structure now complete.

Throughout the month, the floor slabs that support the car parking system were complete, while basement levels one and two have been stripped of props and formwork. Excitingly, these advancements enable Multiplex to lay blockwork walls and install services.

Further up above ground, July has seen the floor slab for level four completed, which is just above the site’s existing Celtic Club facade.

Rising up in height, the tower crane will begin to climb with the core poured at level seven.