Paragon July 2020
Construction update

In the heart of Melbourne’s CBD, Multiplex continues to meet anticipated deadlines with more outstanding progress achieved.

The end of July marks a momentous milestone with the final concrete pour having being completed, the celebration of structural topping out can begin! A great encouragement to the team as we approach completion later this year.

Wrapped in walls of shimmering blue and champagne gold glass, the striking façade is now complete up to Level 35, while the jump form has commenced deconstruction in preparation for the crane removal.

The interiors of each home continue to make headway with the Beulah team commencing quality assurance checks with Multiplex up to Level 15, walking through every apartment, to ensure the best finished product is delivered upon settlement.

Additionally works are continuing on the Residents’ Spaces of Paragon, including the incredible library, spas, professional kitchen linked to private dining room, theatre room and pool. These spaces once complete will become an exclusive entertainer’s club and wellness hub for all residents to enjoy.

Paragon Update