Paragon June 2019
Construction update

Beulah is delighted to share a June construction update, as we wrap up another month of exciting developments on Paragon.

Throughout this month the final level of the Hydraulic Props were removed, with core concrete now poured up to levels three and four. There has also been several slabs poured including level one, all car stacker levels, and a 50 per cent strip out to basement 02 level; with this, came the removal of props and formwork.

Following the pouring of these slabs, the precast was installed on the lift shaft to level one and facade panels have also been put in place at this level.

It was also a thrill to see the first tower crane climb take place, while our Beulah International illuminated jump form signage was also installed; visible from Queen and La Trobe streets.