Construction update

The end of May marks a significant milestone for Paragon as construction continues to
gain momentum.

Throughout the month of May our trusted builders Multiplex have completed the slab for Basement Level 1 as well as the slab Lower Mezzanine level. They have also commenced the formwork for the Level 1 (ground) slab.

Four core pours have also been completed; the core is the heart of the building that will house the lift and the staircase.