Construction update

September has been an incredibly fruitful month at Paragon with construction advancing to the first of the apartment levels – level 8.

The core is now sitting at level 10, with the level 8 slab scheduled to be poured any day now!

An exciting time for everyone with construction set to speed up as works on the tower component rise up to Level 48 over the next 12 months.

Underground, our team has started working on building services, including the car stacker concrete slabs which have been stripped out in preparation for the arrival of the car parking system in October.

Paragon construction apartment level updates